Executive Summary
Coca-Cola Beverages Pakistan Limited (CCBPL) operates multiple manufacturing plants across the country, each needing consistent, dependable perimeter access control for staff, suppliers, and freight vehicles. Rather than a single-site project, this was a nationwide, multi-year engagement—rolling out the same standard of gate automation and access control at one CCBPL plant after another as each site came due.
ASG Systems Pakistan was engaged as the solutions and service provider responsible for planning, supplying, and installing automated gates and access control systems at CCBPL plants nationwide—including Hattar and Multan—across four project phases in 2019, 2021, 2022, and 2024, working with technology partner Centurion.
The brief
The Challenge
As a nationwide beverage manufacturer, CCBPL needed its plant perimeters secured to a consistent standard, even though each plant had its own layout, timeline, and operational constraints:
- Automate heavy-duty perimeter gates at industrial plants handling constant truck and freight traffic.
- Control vehicle and personnel access at each plant without disrupting ongoing manufacturing and logistics operations.
- Deliver the same standard of gate automation and access control across every plant, despite the rollout spanning several years and sites.
- Select equipment rugged enough for continuous industrial use in varied site conditions nationwide.
What we delivered
The Solution: Phased Gate Automation Across the Plant Network
ASG Systems Pakistan installed automated sliding gates and access control at CCBPL plants nationwide, rolling out the same equipment standard plant by plant as each site’s project phase came up.

Component 01
Vehicle Access Checkpoint & Gate
At each plant, a guard booth paired with a heavy-duty automated gate controls vehicle entry—admitting delivery trucks, freight vehicles, and staff traffic through a single, monitored checkpoint.


Component 02
Heavy-Duty Automated Sliding Gates
Large, heavy-duty automated sliding gates, supplied by Centurion, secure each plant’s perimeter entrance—built to handle continuous daily opening and closing cycles in an industrial environment.

Component 03
Commissioning & Control Room Integration
Each gate installation is backed by on-site commissioning work—wiring the control panel, integrating with the guard booth, and testing the system before handover, as part of every phase of the rollout.
Partners
Technology Partner: Centurion
To equip CCBPL’s plants nationwide with dependable, industrial-grade automation, ASG Systems Pakistan partnered with Centurion as the technology and equipment partner for every phase of the rollout. This ensured a consistent standard of automated gate hardware across every plant, regardless of when in the multi-year program that site’s installation took place.
Phased delivery
Rollout Timeline
The project was delivered as a phased, multi-year program across CCBPL’s plant network rather than a single installation:
- 2019Initial gate automation and access control phase at CCBPL plant sites.
- 2021Continued rollout to additional CCBPL plants.
- 2022Further plant sites brought onto the same automation standard.
- 2024Most recent phase, extending gate automation and access control to further plants including Hattar and Multan.
How we did it
Implementation Approach
- 1Site survey at each CCBPL plant to plan gate placement and access control integration ahead of its project phase.
- 2Procurement and staging of automated gate equipment through Centurion for each site.
- 3Civil and electrical works for gate foundations, motor installation, and guard booth control panel wiring.
- 4Installation, calibration, and functional testing of each automated gate before handover.
- 5Coordination with plant security and operations staff at each site for a smooth go-live, repeated across all four project phases.
Outcome
Results & Impact
Across four phases from 2019 to 2024, the rollout gave CCBPL a consistent, nationwide standard of plant perimeter security:
- Automated, heavy-duty gate control at CCBPL plants nationwide, including Hattar and Multan.
- A single, monitored vehicle checkpoint at each plant for trucks, freight, and staff traffic.
- The same Centurion-backed automation standard applied consistently across every site, regardless of rollout year.
- A long-term partnership between ASG Systems Pakistan and CCBPL spanning multiple plants and years.
FAQs
Frequently Asked Questions
What work did ASG Systems Pakistan do for Coca-Cola Beverages Pakistan Limited?
Gate automation and access control across CCBPL plants nationwide, including Hattar and Multan, delivered in phases in 2019, 2021, 2022, and 2024.
Why was the CCBPL project delivered in phases over several years?
CCBPL operates multiple plants across Pakistan, so the rollout was carried out plant by plant over several years rather than all at once, keeping a consistent automation standard across the network.
Who was the technology partner for the CCBPL gate automation project?
Centurion supplied the automated gate and barrier equipment used across the CCBPL plant rollout.
Need gate automation across multiple sites?
ASG Systems Pakistan plans, supplies, and installs automated gates and access control systems for industrial, commercial, and residential sites across Pakistan—whether it’s a single site or a nationwide rollout.